How to Setup Outside Processing in Work Order- Sage 100

Summary

How to set up outside processing in Work Order

Resolution

  1. Select Work Order, Setup, Work Center Maintenance
  2. Define the work center, and select the Outside Processing Work Center check box
  3. Select Work Order, Setup, Operation Code Maintenance
  4. Click Lookup for Work Center, and select the work center code representing the work center to add or maintain
  5. Click Lookup for Operation Code, and enter the operation code representing the operation to assign to the specified work center.
  6. In the Run Time Format list box, type or select the appropriate format:
    • Hours/Operation calculates operation run time in terms of hours per operation. Select this option if it takes more than an hour to complete one operation.
    • Lot calculates operation run time as a fixed amount of time per lot (for example, a setup operation). Select this option if an operation always takes a fixed amount of time.
    • Operations/Hour calculates operation run time in terms of operations per hour. Select this option if more than one operation per hour is completed.
    • Enter the appropriate Rate/Hour and Rate/Piece for both Planned Cost and Planned Cost Divisor fields.
    • The cost is in relation to the parent For example, if the planned cost rate is typically $1.50 per 1000 pieces, you would enter the planned cost rate as 1.50 per piece and a planned cost divisor of 1000. This applies $0.0015 per piece when the operation is processed.
  7. Accept