Steps:
- Open Purchase Orders > P/O Transactions > Requisition Entry.
- Press Tab to accept *** NEW *** as the number in the Requisition Number field. Purchase Orders will assign a requisition number when you post the requisition. If you do not want Purchase Orders to assign the number automatically, you can enter the new number yourself.
- Enter the Vendor number or select it using the Finder.
- You can skip the vendor number and enter a vendor name—such as for a new vendor—or you can skip the vendor fields entirely.
- You can click the New button to add a new vendor record in Accounts Payable.
- Enter a requisition date, a date required, and an expiration date.
- Note: If the requisition is not completed by the expiration date, it will be deleted when you run Day End Processing.
- Choose whether this requisition is on hold.
- Note: You cannot create purchase orders from on-hold requisitions.
- If you are approving a requisition that was previously entered:
- You must have requisition approval security rights.
- You must log on with your own ID.
- You must remove the On Hold status from the requisition, and then post it.
- Choose the Job Related option if you use the Project and Job Costing module and this requisition is for a job. If the purchase requisition is job-related, all items must be for particular contracts, projects, and
categories in Project and Job Costing. Also, you cannot add serialized items or items assigned to lots to job-related transactions.
Instead, you must order them as non-job-related items, receive them into inventory, and then use the Material Usage screen in Project and Job Costing to move them from inventory to jobs. - In the Requested By field, enter the name of the person requesting the order.
- Note: If you use Sage 300 Payroll, you can select the requester from the Finder.
- Enter the location where you want the goods delivered, and enter a requisition description and reference.
- Enter requisition details. You can enter details directly in the detail entry table. (Use the tab key to move through the columns.)
- Note:
- Some columns may not be displayed. Purchase Orders lets you hide columns and change the column order.
- To enter a new detail line, you may have to press Insert.
- Alternatively, you can click Detail or press F9 to enter a detail on the Detail Items screen, which displays all the fields for one detail. Enter the following information for each detail:
- If this is a job-related requisition:
- Double-click the Contract field and enter the contract number, or click the Contract column heading to select a contract number using the Finder.
- Enter the project and category to which you are allocating items.
- Double-click the Item Number field and enter an item number, or click the Item Number column heading to select an item number using the Finder.
- Enter vendor information.
- Note: You can leave the vendor fields blank, and you can specify different vendors on
each line. You can create more than one PO from a single requisition.
- Note: You can leave the vendor fields blank, and you can specify different vendors on
- Enter the location for the detail.
- Note: The location for each detail defaults from the Location field in the header fields.
- Enter a Quantity Ordered.
- To change currency exchange rates in a multicurrency system, click Detail or press F9 to open the Detail Items screen.
- If this is a job-related requisition:
- Note:
- To check the totals for the requisition, click the Totals tab.
- Click Post to post the purchase requisition.
Note: If you do not have the security right to approve requisitions, the requisition will be on hold after you post it, and the Approval Status field will display “Entered.”